Thursday, January 6, 2011

The Basement Project - Update 2

Four days into the Project, the following has been accomplished:
  • The framing for all walls has been completed
  • The door frame for the pocket door to the mechanicals storage area is in place
  • Electrical lines have been run and all light boxes, switches, and outlets have been installed and/or moved as appropriate
  • All water lines for the powder room have been installed

Lots accomplished in four days. I don't think that this Project will be completed in two weeks as originally promised, but I am betting that it will come in "under" the date of January 28 as established by noted handicapper, "John Bocabella."