- Despite the snow that caused numerous school closings and delays, the contractors have not missed a day of work.
- All drywall has been erected, sanded, primed, and have had one coat of paint applied. This includes the interior walls and ceiling of the powder room.
- Water lines and valves have been installed for the powder room.
- Baseboards have been installed where needed.
- All doors and have been hung, including the trim around the doors, with one coat of paint applied.
- All electrical lines, light boxes, switches, and outlets have been installed.
The biggest job that remains will be tiling the bathroom floor and installing the vanity, sink, and commode.
The original two week estimate for completion has not been met, but we never really expected that all would be done in two weeks. We are confident, however, that by this time next week, the job should be done.
Can the return of the "Executive Game" be far behind?